Seacliff pumping station and compact construction site overlooking San Francisco Bay
← Projects

End client: San Francisco Public Utilities Commission (SFPUC)

Seacliff 2 Pump Station & Force Main (San Francisco)

A short crossing. A narrow window. A carefully controlled installation between the utilities that keep a neighborhood running.

Watch Film ↓
CSLB #1115805

SEACLIFF 2 PUMP STATION AND FORCE MAIN UPGRADES

The challenge was
the space between.

Phoenix Boring completed a 130-foot guided crossing with permanent 16-inch steel casing in March 2026, working with Western Water on SFPUC’s Seacliff 2 wastewater pump station and force main upgrade.

Water, gas, sewer, power, telecommunications and drainage infrastructure occupied the corridor at different depths. The task was to navigate a narrow three-dimensional path between them, while limiting surface disruption on a sensitive residential street.

130 ft
Trenchless installation
16 in
Permanent steel casing
Mar 2026
Phoenix field work complete
≈6 mm
Pilot arrival deviation from target
General contractor Western WaterTrenchless contractor Phoenix Boring

01 / UNDERSTANDING THE CORRIDOR

Precision starts
before the bore.

Plans, utility markings, ground-penetrating radar and vacuum potholing informed the alignment. Guided boring with 4-inch pilot tubes gave the team the control needed to work within that constrained route.

The casing was installed at an approximate depth of 5 to 8 feet. The trenchless approach reduced the surface footprint around residents, pedestrian routes, traffic and existing trees.

Optical guidance equipment in the Seacliff launch pit
Optical pilot guidance helped control line and grade through the crowded utility corridor.
Phoenix ADB48 platform inside the compact shored launch pit at Seacliff
The ADB48 platform operating in guided boring mode within the compact launch pit.

02 / WORKING WITH THE SPACE AVAILABLE

A compact footprint.
A coordinated operation.

The planned launch pit measured approximately 20 feet long by 10 feet wide. Phoenix’s proprietary ADB48 platform worked within a site that also had to accommodate the power unit, generator, lifting equipment and excavated material.

There was no room to store every casing and auger section at once. Progressive deliveries and carefully planned lifting operations kept the work moving within the available footprint.

03 / THE LAST FEW FEET MATTER

A diagonal reception.
No room to overshoot.

Existing utilities forced the receiving pit into the only available opening, with the casing entering diagonally through a corner.

Each five-foot pilot section had to advance far enough to expose its connection, but not so far that it struck the opposite wall. Visual indicators and radio communication between the two crews controlled each cycle.

Crew members working at the casing entry in the constrained reception pit
The reception pit’s geometry shaped how each section could be disconnected and removed.
Guided pilot emerging into the reception pit
The pilot arrived approximately 6 mm from its planned target.

04 / FIELD RESULT

Built with control.
Completed with precision.

The work was completed in eight eight-hour shifts, with no reported damage to existing utilities.

Dense sand required careful adjustment of the pilot’s advance rate. The crew monitored excavated material volumes and survey control throughout the installation.

This project demonstrates why precision, a compact operating footprint and field coordination can matter more than bore length in a heavily congested urban corridor.

SEE THE WORK

Watch the project film

Case study based on Roberto Zillante’s June 2026 Spanish-language article prepared for LAMSTT, “Frente al Golden Gate: Precisión sin zanja en un corredor congestionado.”