End client: San Francisco Public Utilities Commission (SFPUC)
Seacliff 2 Pump Station & Force Main (San Francisco)
A short crossing. A narrow window. A carefully controlled installation between the utilities that keep a neighborhood running.
Watch Film ↓SEACLIFF 2 PUMP STATION AND FORCE MAIN UPGRADES
The challenge was
the space between.
Phoenix Boring completed a 130-foot guided crossing with permanent 16-inch steel casing in March 2026, working with Western Water on SFPUC’s Seacliff 2 wastewater pump station and force main upgrade.
Water, gas, sewer, power, telecommunications and drainage infrastructure occupied the corridor at different depths. The task was to navigate a narrow three-dimensional path between them, while limiting surface disruption on a sensitive residential street.
- 130 ft
- Trenchless installation
- 16 in
- Permanent steel casing
- Mar 2026
- Phoenix field work complete
- ≈6 mm
- Pilot arrival deviation from target
01 / UNDERSTANDING THE CORRIDOR
Precision starts
before the bore.
Plans, utility markings, ground-penetrating radar and vacuum potholing informed the alignment. Guided boring with 4-inch pilot tubes gave the team the control needed to work within that constrained route.
The casing was installed at an approximate depth of 5 to 8 feet. The trenchless approach reduced the surface footprint around residents, pedestrian routes, traffic and existing trees.


02 / WORKING WITH THE SPACE AVAILABLE
A compact footprint.
A coordinated operation.
The planned launch pit measured approximately 20 feet long by 10 feet wide. Phoenix’s proprietary ADB48 platform worked within a site that also had to accommodate the power unit, generator, lifting equipment and excavated material.
There was no room to store every casing and auger section at once. Progressive deliveries and carefully planned lifting operations kept the work moving within the available footprint.
03 / THE LAST FEW FEET MATTER
A diagonal reception.
No room to overshoot.
Existing utilities forced the receiving pit into the only available opening, with the casing entering diagonally through a corner.
Each five-foot pilot section had to advance far enough to expose its connection, but not so far that it struck the opposite wall. Visual indicators and radio communication between the two crews controlled each cycle.


04 / FIELD RESULT
Built with control.
Completed with precision.
The work was completed in eight eight-hour shifts, with no reported damage to existing utilities.
Dense sand required careful adjustment of the pilot’s advance rate. The crew monitored excavated material volumes and survey control throughout the installation.
This project demonstrates why precision, a compact operating footprint and field coordination can matter more than bore length in a heavily congested urban corridor.
SEE THE WORK
Watch the project film
Case study based on Roberto Zillante’s June 2026 Spanish-language article prepared for LAMSTT, “Frente al Golden Gate: Precisión sin zanja en un corredor congestionado.”