Skip to content
Phoenix Boring
Start a conversation
Menu

For Investors

Vertically integrated, tech-enabled trenchless undergrounding service provider

We design the equipment, build it in-house and put it to work installing underground utilities. Our modular platform lets the same base machine switch boring methods as the ground and the job demand.

CSLB #1115805

THE UNDERGROUNDING CHALLENGE

The cost of what you can’t see.

Utilities need to harden power grids and replace aging water and sewer lines. Trenchless construction can keep roads open and limit surface disruption. But what lies between the launch and reception pits can make a crossing harder to price.

CROSSING PROFILEIllustrative crossing · not to scale
  • Stable ground
  • Unstable ground
  • Bedrock
  • Proposed pipe

Two samples. One best guess.

Before sampling, the ground profile is unknown. Two samples tell us what’s at the ends of the crossing. Everything in between is an estimate.

Same layers. Different depths.

Suppose the crew can sample four more spots along the route, all from dry ground. Each sample shows the layers at that location, not the full picture.

When the ground changes.

The revised profile puts unstable ground and bedrock in the pipe’s path. What happens if the crew sticks with the setup it picked for stable ground?

WHY IT SHOWS UP IN THE PRICE

What we call the geological risk fee.

It’s not a separate charge. It’s the contingency contractors build into bids to cover possible delays, equipment changes, or specialist help when ground conditions differ from the plan.

Phoenix’s approach: Our modular platform lets us change boring methods on the same base machine when conditions allow. If a crossing needs something we don’t already have, we can engineer it in-house. That doesn’t eliminate geological uncertainty, but it gives us more ways to handle it.

Our Solution

Change the method, not the machine.

Phoenix’s 6-in-1 platform gives crews options a single-purpose machine doesn’t. The same base machine adapts to different diameters, alignment tolerances and ground conditions by changing tooling, settings or the boring method itself.

Adapt when the ground changes.

Conventional methods cover many crossings. Assisted Dynamic Boring is built for unstable ground, and Jet Bore is in development for hard rock. If a crossing calls for a tool we don’t have, we can design and build it in-house.

Bid with more ways to finish.

We compete on straightforward crossings, but our advantage is greatest in difficult or variable ground. Having more than one way to finish a drive reduces our reliance on any single ground assumption and lets us pursue more jobs.

Expand where it matters most.

We look first at regions where difficult or mixed geology can limit the number of contractors equipped for the work. Those are the markets where the ability to change methods on the same machine can matter most.

Company Traction

From first bid to multi-crew operations.

Phoenix began operating in Q3 2024. Track how contract bookings, financing and field capacity grew as the early jobs turned into a repeatable construction business.

Operating Progress

Contracts, capital and field capacity

USD millions and operating counts · selected checkpoints

  • Contract bookings
  • Capital raised
  • Full crews
  • Active Machines
Bookings through Q2 2026 include the approximately $2M ARPA-E cooperative agreement awarded in Q4 2024. The Q4 2024 point shows the award alone, not total bookings. The Q3 2026 point shows an approximately $12M August estimate for forward commercial bookings, with no ARPA-E amount added. It is not a quarter-end or recognized-revenue figure. Active Machines counts equipment available for deployment. The capital series shows documented SAFE and Seed financing; earlier SAFE proceeds are counted once, not again upon conversion. Blank periods are not estimated.
Quarterly data and milestone notes
QuarterContract bookingsCapital raisedFull crewsActive MachinesMilestone
Q3 2024—~$1MFounder-led—Operations began with a lean team and project partnerships; first SAFE financing.
Q4 2024~$2M ARPA-E award; total not reported~$1.34M—1 recommissionedFirst public bid won. ARPA-E cooperative agreement became active; first ADB recommissioned.
Q1 2025~$2.6M~$1.93M—2Second ADB recommissioned. Early SAFE capital shown as the cumulative tranches in the company presentation.
Q2 2025~$3.5M~$2.23M—2Early SAFE funding reached about $2.23M; first project accessories fabricated in-house.
Q3 2025~$5M~$2.23M—2Field delivery advanced.
Q4 2025~$6M~$2.23M—2Field delivery continued, including Paradise Drive.
Q1 2026~$8M~$4.64M documented12Priced Seed closed; previously issued SAFEs converted. First full crew mobilized for North Perris.
Q2 2026~$10M~$4.64M documented12Commercial bookings reached approximately $8M, plus the ARPA-E award.
Q3 2026~$12M in forward bookings (August)~$5.64M documented23July’s $1M working-capital SAFE supported the summer workload. Two full crews first split at Sunnyslope, and a third machine was available by Q3.

June 2024

Phoenix founded

Operations began the next quarter with a founder-led team and early SAFE financing.

Q4 2024

Public work and PyroHDD

First public bid won and a U.S. Department of Energy ARPA-E cooperative agreement launched PyroHDD development.

2025

From shop to site

Recommissioned a second machine, fabricated project tooling in-house and grew the commercial book to about $4M.

Q1 2026

Priced Seed

Early SAFEs converted. The round added new capital to support the move toward multi-crew operations.

Q3 2026

Working capital and two full crews

A $1M SAFE supported the summer construction workload. The first two-crew split came at Sunnyslope.

Operating Model

One team. From shop to site.

Engineering

Our field crews and engineers work together to identify where a method, cutter or adapter needs to change, then test the result.

Manufacturing

Building equipment and tooling in-house lets us adapt a machine to the job rather than accept the limits of an off-the-shelf setup.

Field execution

Phoenix earns revenue delivering trenchless crossings. New engineering goes back into the field with the team that helped define it.

Trenchless construction work on the PG&E crossing in Cupertino

Our Founding Story

From prototype to paid work.

Phoenix Boring grew from two complementary technologies: Zilper’s approach to unstable ground and Petra’s approach to hard rock. A PG&E crossing in California helped turn that engineering into a contractor that designs, builds, and operates its own equipment.

Read our story

Investor Conversations

What comes after Seed?

Our ambition is to make Phoenix a national jack-and-bore contractor and, over time, to bring the platform to international markets. The next step is delivering more crossings with multiple crews and entering regions where complex geology gives our equipment a meaningful advantage.

Hardening a grid that also has to grow.

Targeted undergrounding can reduce exposure to wildfire. At the same time, utilities need to add electrical infrastructure to support rising loads, including AI data centers. Both needs create crossings where the grid must expand without unnecessarily disrupting the surface.

DOE undergrounding guide · Berkeley Lab data center report

U.S. Department of Energy · ARPA-E

PyroHDD: an R&D program for underground power.

Backed by ARPA-E’s GOPHURRS program, Phoenix is developing a horizontal directional drilling system intended to install electrical conduit through mixed geology, including hard rock. PyroHDD pairs thermal spallation with other drilling capabilities. The goal is to make more underground routes practical; the system is in development, not a commercial service.

Read the DOE project description

Explore PyroHDD